Glass Recycling Plant, Glassdon Recycling

This involved the construction of a 2000m2 recycling plant over 5 levels.  The scope of works included:

  • site clearance of 2 acres
  • placing of concrete yard
  • retaining walls
  • reinforced concrete ground floor construction
  • steel clad superstructure

This project was carried out in close collaboration with Specialist M&E contractors BT-Wolfgang Binder GmbH.  All works were completed on time and within budget.  The successful delivery of this project has seen a number of repeat orders from the Client.

Client:       Glassdon Recycling
Architect:  Teague and Sally
Duration:   5 Months (on budget and time)
  • New Optical Glass Sorting Plant
  • Reinforced Concrete to Collect Sorted Glass
  • Storage Silos
  • Intake Conveyor
  • Aerial view of Silos